Construction Update –

  • 3 Million Gallon Lower Tank Site Rough Grading
    • ~95% Complete
    • Remaining Work- Complete Subdrain Installation, Tank Pad Backfill
    • Estimated completion date- Monday 12/4/17
Tank Site Subdrain Installation

Tank Site Subdrain Installation

  • Padre Lane Improvements
    • ~95% Complete
    • New Railroad Track Operational, Sewer Line and Domestic Water Line Tested and Joined to Municpal. Complete Contract by Friday 12/8/17
Padre Lane Railroad Track Replacement

Padre Lane Railroad Track Replacement

Final Sewer Tie-In to Packing House

Final Sewer Tie-In to Packing House

  • Removal of Jurisdictional Drainage Courses
    • 100% Complete

Dec1-17 Picture - 003 Dec1-17 Picture - 004 Dec1-17 Picture - 005

  • Removal of Jurisdictional Drainages Under Supervision of Biologist and Cultural Resource Monitor.
    • Remaining Work- Complete Orange Bio Fence Installtion
  • Phase 1 Backbone Street Utility Undercut
    • ~40% Complete
    • Remaining Work- Continue Undercut to Removal Oversize Rock Ahea of Granite Backfilling Operations with Soil.
Santa Paula Street Utility Undercut/Overexcavation

Santa Paula Street Utility Undercut/Overexcavation

  • Phase 1 Rough Grading
Grading Start at Milestone 1 Area

Grading Start at Milestone 1 Area

Dec1-17 Picture - 008

Milestones schedule for upcoming week

  • Lower Tank Site- Complete subdrain installation and pad backfilling
  • Padre Lane Improvements- Complete all utility and railroad work
  • Jurisdictional Drainage Related- Complete installation of bio fence
  • Phase 1 Rough Grading- Continue progress towards completion of Phase 1 Grading Milestone 1
  • Complete offsite haul-off of Phase 2 orchard grindings