• Recorded Final Tract Map 5854 on 12/21
  • Started work for Rule 20 conversion on 1/15
  • Completed Padre Lane Sewer & Water Improvements
  • Awarded contract to Toro Enterprises for phase 1A Backbone Wet Utilities
  • CPUC approved the Petition for Modification
  • Executed agreement with Crimson Oil for relocation of two oil transmission pipelines
  • Completed relocation of SCE poles