Construction Update –

  • 3 Million Gallon Lower Tank Site Rough Grading
    • ~90% Complete
    • Remaining Work- Complete V-Swales, Pad Backfill, Drain Installation, Stabilize
Tank Site Slope Cut and Pad Overexcavation

Tank Site Slope Cut and Pad Overexcavation

  • Padre Lane Improvements
    • ~75% Complete

Remaining Work- Construct New Railroad Track and Crossing, Backfilling, Test & Chlorinate Water Line, Test Sewer, Joins to Municpal, Repave

Padre Lane Temp Railroad Track Removal

Padre Lane Temp Railroad Track Removal

Water Line Install Beneath Exist. Pipelines/Utilities

Water Line Install Beneath Exist. Pipelines/Utilities

  • Removal of Jurisdictional Drainage Courses
    • ~10% Complete
    • Remaining Work- Continue Removal of Drainage Courses with Granite Construction and Biologist.
Removal of Jurisdictional Drainage Along Padre Lane Entrance with Oversight from Biologist and Cultural Resource Monitor.

Removal of Jurisdictional Drainage Along Padre Lane Entrance with Oversight from Biologist and Cultural Resource Monitor.

Nov17-17 Picture - 005

  • Phase 1 Backbone Street Utility Undercut
    • ~30% Complete

Remaining Work- Continue Undercut to Removal Oversize Rock Ahea of Granite Backfilling Operations with Soil.

Santa Paula Street Utility Undercut/Overexcavation

Santa Paula Street Utility Undercut/Overexcavation

Milestones schedule for upcoming week (Short Week)

  • Lower Tank Site- Begin subdrain installation and pad backfilling, complete drainage swales
  • Padre Lane Improvements- Complete utility line backfill and railroad track subgrade preparations and ballast installation
  • Jurisdictional Drainage Removal- Complete removal/disturbance of drainage courses
  • Phase 1 Rough Grading- Granite to complete equipment mobilizations and construction water development for Rough Grading start Monday Nov. 27.